Choosing a Baseline Microsoft Project has many baselines, but only one group of 'Actual' values.Rather than duplicate multiple baselines, Intelli Gantt works with a current baseline and names them 'Estimates'.This makes greater sense for the Share Point team members who may not be exprienced in project management nomenclature and still allows project managers to convey important baseline information.

Update MS Project Estimates By default this is set to false when you first start working with Intelli Gantt because Microsoft's automatic calculations might give you some surprising results if you're not aware estimates are being updated.

You can always apply Intelli Gantt's cached estimates to the project by selecting Intelli Gantt-Apply Estimates.

Updating MS Project Actuals By default actuals are also not updated automatically by Intelli Gantt right out of the box.

Similar to the estimates, updated actuals will cause Microsoft Project to automatically recalculate the project.

You can always apply Intelli Gantt's cached actuals to the project by selecting Intelli Gantt-Apply Actuals.

If you would like to run your project so that Share Point team members can update 'Actual Work' and 'Remaining Work', you should enable this field.

This will allow Intelli Gantt to make the necessary updates to capture Actual Work and Remaining Work from Share Point and correctly update Microsoft Project (be sure 'Update MS Percent Complete' is turned off in this case).

This form allows you to work with more sophisticated project management reporting patterns and provides greater control how Percent Complete, Baselines (what we call Estimates) and Actuals are updated in Microsoft Project 2007.

These settings control what happens automatically, which in turn can affect the automatic calculations within Microsoft Project.(More on Calculations) Update MS Project Percent Complete By default this is set to true when you first start working with Intelli Gantt because many project managers are looking for a simple way to share tasks and receive progress reports in the form of percent complete.

However, if you would rather team members report their 'Actual Work' and 'Remaining Work', then you will need to uncheck this field so that Intelli Gantt does not update it.

The reason is Microsoft Project will assign arbitrary percent complete values in this field in some situations.